Better Streets Safer City Program Summary and Project Status



In 2017, the voters of Oklahoma City approved an unprecedented investment in streets, traffic infrastructure and sidewalks along streets.   This initiative, known as Better Streets, Safer City was funded by the approval of a bond issue that is expected to sell bonds for the next decade and a one-cent sales tax that will be collected through March of 2020.   The initiative is expected to provide a total of $766,580,000 dollars for streets, traffic infrastructure, trails and sidewalks along streets.



Projects Completed

Arterial Resurfacing: SE 29th Street from Shields Boulevard to I-35

Arterial Resurfacing: SW 29th Street, Mustang Road to Morgan Road

Arterial Resurfacing: NW 30th St from N Western Ave to N Pennsylanvia Ave

Arterial Resurfacing: N Bryant Ave from NE 4th St to NE 10th St

Arterial Resurfacing: Bryant Avenue from SE 89th Street to SE 104th Street

Arterial Resurfacing: Cimarron Road, SW 74th Street to SW 15th Street

Arterial Resurfacing: SW 104th St from N Morgan Rd to S County Line Rd

Arterial Resurfacing: SW 104th St from S County Line Rd to S Council Rd

Arterial Resurfacing: SE 104th St from S Henney Rd to S Choctaw Rd

Arterial Resurfacing: SE 104th St from S Hiwassee Rd to S Henney Rd

Arterial Resurfacing: SE 104th St from S Indian Meridian to S Triple X Rd

Arterial Resurfacing: SW 104th St from S Rockwell Ave to S MacArthur Blvd

Arterial Resurfacing: SW 104th Street between Rockwell Avenue and Council Road

Arterial Resurfacing: SW 104th Street from Penn Avenue to Western Avenue

Arterial Resurfacing: NE 10th Street between Bryant Ave and N Martin Luther King Ave

Arterial Resurfacing: SW 119th St from S Portland Ave to S May Ave

Arterial Resurfacing: SW 119th St from S Western Ave to City Limits

Arterial Resurfacing: SW 119th Street from Czech Hall Road to Cemetery Road

Arterial Resurfacing: SW 119th Street from Mustang Road to Czech Hall Road

Arterial Resurfacing: SW 119th Street, I-44 to Meridian Avenue

Arterial Resurfacing: NW 122nd St from N MacArthur Blvd to N Meridian Ave - Child project for PC-0659

Arterial Resurfacing: NW 122nd St from N Meridian Ave to N Portland Ave - Child project of PC-0659

Arterial Resurfacing: NW 122nd Street between Pennsylvania Avenue and Western Avenue

Arterial Resurfacing: NE 150th Street between N. Henney Road and Choctaw Road

Arterial Resurfacing: SW 15th St from I-44 to S Agnew Ave

Arterial Resurfacing: SE 164th Street between Douglas Blvd and Post Road

Arterial Resurfacing: NW 164th Street from Western Avenue to City Limits

Arterial Resurfacing: NW 16th St from N May Ave to N Portland Ave

Arterial Resurfacing: NW 192nd St from N Portland Ave to N May Ave PREVIOUS PC-0372 (2014)

Arterial Resurfacing: NW 23rd Street from Sara Rd to E. Overholser Drive

Arterial Resurfacing: SW 25th Street from Walker Avenue to Western Avenue

Arterial Resurfacing: SW 29th St from Portland extending east 1000 ft to RR tracks

Arterial Resurfacing: SW 29th St from RR tracks to S May Ave

Arterial Resurfacing: SE 29th St from S Bryant Ave to S Eastern Ave

Arterial Resurfacing: SW 29th Street from Cimarron Road to Gregory Road

Arterial Resurfacing: SW 29th Street from Council Road to County Line Road

Arterial Resurfacing: SW 29th Street from County Line Road to Morgan Road

Arterial Resurfacing: SW 29th Street from Rockwell avenue to Council Road

Arterial Resurfacing: W Memorial Rd (Eastbound) from N Meridian to Lake Hefner Parkway

Arterial Resurfacing: W Memorial Rd (Westbound) from Lake Hefner Parkway to N May Ave Completed by ODOT JP 30230(04) / PC-0518 in January 2019.

Arterial Resurfacing: W Memorial Rd (Westbound) from N MacArthur Blvd to N Meridian Ave

Arterial Resurfacing: W Memorial Rd (Westbound) from N Meridian Ave to Lake Hefner Parkway

Arterial Resurfacing: Rockwell Avenue from NW 150th Street to NW 164th Street

Arterial Resurfacing: S Rockwell Avenue from Reno Avenue to the I-40 Service Road

Arterial Resurfacing: SW 36th St from S May Ave to S Pennsylvaia Ave

Arterial Resurfacing: SW 36th St from S Pennsylvania Ave to S Western Ave

Arterial Resurfacing: NE 36th Street, Lincoln to I-35

Arterial Resurfacing: SE 44th St from S Anderson Rd to S Hiwassee Rd

Arterial Resurfacing: SE 44th St from S Eastern Ave to S Bryant Ave

Arterial Resurfacing: SE 44th St from S High Ave to S Eastern Ave

Arterial Resurfacing: SE 44th St from S Santa Fe Ave to S High Ave

Arterial Resurfacing: SW 44th St from S Sara Rd to S Morgan Rd

Arterial Resurfacing: SW 44th Street, Sara Road to Frisco Road

Arterial Resurfacing: NE 4th St from N MLK Blvd to N Bryant Ave

Arterial Resurfacing: NW 4th St from N Western Ave to N Broadway Ave

Arterial Resurfacing: NW 50th St from N Independance Ave to N May Ave

Arterial Resurfacing: NW 50th St from N Meridian Ave to N Tulsa Ave

Arterial Resurfacing: NW 50th St, from Tulsa east to I-44

Arterial Resurfacing: SW 59th St from S Morgan Rd to S County Line Rd

Arterial Resurfacing: NE 63rd Street between Air Depot Blvd. to Midwest Blvd.

Arterial Resurfacing: NE 63rd Street between Bryant Ave and Air Depot Blvd.

Arterial Resurfacing: NW 63rd Street from N. Western Avenue to Broadway Extension

Arterial Resurfacing: SW 74th St from Regina Ave to MacArthur Blvd

Arterial Resurfacing: SW 74th St from Rockwell Ave to Council Rd

Arterial Resurfacing: SW 74th St from S Council Rd to Highway 152

Arterial Resurfacing: SE 74th Street from Hiwassee Road to Henney Road

Arterial Resurfacing: SW 89th St from S Pennsylvania Ave to S Western Ave

Arterial Resurfacing: SE 89th St from S Sunnylane Rd to S Sooner Rd

Arterial Resurfacing: SE 89th Street from Eastern Avenue to Bryant Avenue

Arterial Resurfacing: SW 89th Street, Council Road to County Line Road

Arterial Resurfacing: Agnew Avenue from SW 44th Street to SW 29th St

Arterial Resurfacing: S Air Depot Blvd from SE 164th to SE 179th St

Arterial Resurfacing: W Britton Rd from N Western to I-235

Arterial Resurfacing: W Britton Rd from Piedmont Rd (Hwy 4) to N Mustang Rd

Arterial Resurfacing: N Classen Blvd from NW 10th St to NW 16th St

Arterial Resurfacing: Corridor on S Peebly Rd from SE 89th to SE 44th, and SE 44th from Peebly Rd to Turnpike

Arterial Resurfacing: N Council Rd from Memorial Rd to NW 150th St

Arterial Resurfacing: S Council Rd from SW 104th St to SW 89th St

Arterial Resurfacing: S Council Rd from SW 89th St to SW 74th St

Arterial Resurfacing: S Council Rd from SW 8th St to W Reno Ave

Arterial Resurfacing: N County Line Rd from W Britton Rd to W Hefner Rd

Arterial Resurfacing: N County Line Road between NW 150th Street to NW 164th Street

Arterial Resurfacing: S Czech Hall Rd from SW 29th St to SW 15th St

Arterial Resurfacing: S Czech Hall Rd from SW 59th St to SW 44th St

Arterial Resurfacing: S Czech Hall Road from SW 29th Street and SW 44th Street

Arterial Resurfacing: E Memorial Rd from N Kelley Ave to N Eastern Ave

Arterial Resurfacing: East Wilshire Boulevard from Broadway Extension to Kelley Avenue

Arterial Resurfacing: Frisco Road from Hefner Road to NW 122nd Street

Arterial Resurfacing: Frisco Road from Memorial Road to NW 150th Street

Arterial Resurfacing: Gregory Road from SW 59th Street to SW 74th Street

Arterial Resurfacing: S Harrah Rd from SE 149th St to SE 134th St

Arterial Resurfacing: S Harrah Rd from SE 89th St to I-40

Arterial Resurfacing: Harrah Road from SE 104th street to SE 119th Street

Arterial Resurfacing: Harrah Road from SE 89th Street to SE 104th Street

Arterial Resurfacing: W Hefner Rd from N MacArthur Blvd to N Meridian Ave - Child

Arterial Resurfacing: W Hefner Rd from N Meridian Ave to N Portland Ave

Arterial Resurfacing: W Hefner Rd from N Rockwell Ave to N MacArthur Blvd - child

Arterial Resurfacing: W Hefner Road from Pennsylvania to Western

Arterial Resurfacing: S High Ave from SE 59th St to SE 44th St

Arterial Resurfacing: N Hiwassee Rd from NE 36th St NE 50th St

Arterial Resurfacing: I-240 Service Rd from S Penn Ave to S Western Ave

Arterial Resurfacing: N Kelley Ave from Memorial Rd to city limit

Arterial Resurfacing: N Kelley Ave from NE 50th St to NE 63rd St

Arterial Resurfacing: N MacArthur Blvd from NW 122nd St to Memorial Rd - Child project for PC-0659

Arterial Resurfacing: S MacArthur Blvd from SW 29th St to SW 22nd St

Arterial Resurfacing: S MacArthur Blvd from SW 44th St to SW 29th St

Arterial Resurfacing: N Martin Luther King Ave from NE 36th St to NE 50th St

Arterial Resurfacing: N May Ave from NW 63rd St to W Wilshire Blvd

Arterial Resurfacing: S May Ave from SW 59th St to SW 44th St

Arterial Resurfacing: W Memorial Rd (Eastbound) from N MacArthur Blvd to N Meridian Ave

Arterial Resurfacing: N Meridian Ave from NW 63rd St to NW Expressway

Arterial Resurfacing: N MLK Ave from NE 10th St to NE 23rd St

Arterial Resurfacing: N MLK Blvd from NE 4th St to NE 10th St

Arterial Resurfacing: S Morgan Rd from SW 104th St to SW 89th St

Arterial Resurfacing: S Morgan Rd from SW 44th St to SW 59th St

Arterial Resurfacing: Morgan Road, SW 44th Street to SW 59th Street

Arterial Resurfacing: S Mustang Rd from SW 104th St to SW 89th St

Arterial Resurfacing: N. Meridian Avenue from NW 122nd Street to Hefner Road

Arterial Resurfacing: Newcastle Road from Council to Meridian

Arterial Resurfacing: S Peebly Rd from SE 59th St to SE 44th St

Arterial Resurfacing: N Pennsylvania Ave from NW 23rd St to NW 36th St

Arterial Resurfacing: N Portland Ave from NW 36th St to NW 50th St

Arterial Resurfacing: S Post Rd from SE 44th St to SE 29th St

Arterial Resurfacing: S Post Rd from SE 59th St to SE 44th St

Arterial Resurfacing: W Reno Ave (Eastbound) from N Rockwell to N MacArthur Blvd

Arterial Resurfacing: W Reno Ave (Westbound) from N Rockwell to N MacArthur Blvd

Arterial Resurfacing: W Reno Ave from N May Ave to N Pennsylvania Ave

Arterial Resurfacing: Reno Avenue from Frisco Road to Richland Road

Arterial Resurfacing: Richland Road, SW 15th Street to Reno Avenue

Arterial Resurfacing: Richland Road, SW 44th Street to SW 59th Street

Arterial Resurfacing: N Rockwell Ave from NW 122nd St to Memorial Rd

Arterial Resurfacing: N Rockwell Ave from W Britton Road to W Hefner Rd

Arterial Resurfacing: S Santa Fe Ave from SE 89th St to I-240

Arterial Resurfacing: S Santa Fe Ave from SW 104th St to SW 89th St

Arterial Resurfacing: Sara Road from NW 23rd Street to NW 36th Street

Arterial Resurfacing: Shields Blvd. from SE 25th Street to SE 29th Street

Arterial Resurfacing: N Sooner Rd from NE 63rd St to E Wilshire Blvd

Arterial Resurfacing: N Villa Ave from NW 16th to NW 23rd St

Arterial Resurfacing: S Walker Ave from I-240 to SW 59th St

Arterial Resurfacing: S Walker Ave from SW 29th to Oklahoma River - Child

Arterial Resurfacing: S Walker Ave from SW 44th St to SW 29th St

Arterial Resurfacing: S Walker Ave from SW 59th St to SW 44th St

Arterial Resurfacing: S Walker Avenue from SW 74th Street and SW 89th Street - Child

Arterial Resurfacing: N Western Ave from NW 23rd St to NW 36th St

Arterial Resurfacing: N Western Ave from NW 50th St to NW 63rd St

Arterial Resurfacing: N Western Ave from W Britton Rd to W Hefner Rd

Arterial Resurfacing: N Western Ave from W Hefner Rd to NW 122nd St

Arterial Resurfacing: N Western Ave from W Wilshire Blvd to W Britton Rd

Arterial Resurfacing: W Wilshire Blvd from N May Ave to Dorset Dr

Arterial Resurfacing: Wilshire Blvd from Olie Ave to Broadway Ext

Bike Lanes: On N. Shartel Ave. to connect to the Deep Fork Creek Trail alignment through Zachary Taylor Park - Chiild Project

Intersection Improvements: Broadway Extension and NE 122 St

Intersection Improvements: N Council Rd and NW 82nd St

Intersection Improvements: N Council Road and NW 113 Street

Intersection Improvements: S Eastern Avenue and SE 89th Street

Intersection Improvements: Highland Park Boulevard and N Pennsylvania Avenue

Intersection Improvements: S Portland Avenue and SW 119th Street

Intersection Improvements: Widen N Rockwell Avenue for left turn lanes at NW 112 Street

Residential Resurfacing: Area bound by High, Santa Fe, SE Grand and SE 29th St. (East 1/2)

Residential Resurfacing: Area bound by Kelley Ave, MLK, NE 23rd St, and NE 36th St (Three Quarters)

Residential Resurfacing: Area bound by Kelley Ave, MLK, NE 23rd St, and NE 36th St (Three Quarters)

Residential Resurfacing: Area bound by Kelley Ave, MLK, NE 36th St, and NE 50th St

Residential Resurfacing: Area bound by May, I-44, SW 89th and SW 104th St

Residential Resurfacing: Area bound by May, I-44, SW 89th and SW 104th St

Residential Resurfacing: Area bound by May, I-44, SW 89th and SW 104th St

Residential Resurfacing: Area bound by N Cemetery Rd, N Czech Hall Rd, W Reno Ave and NW 10th St

Residential Resurfacing: Area bound by N Santa Fe Ave, N Kelley Ave, NW 50th St and NW 36th St

Residential Resurfacing: Area bound by NW 50th, I-44, May and Hefner Parkway / Phase I

Residential Resurfacing: Area bound by Pennsylvania, Western, 164th and 178th St

Residential Resurfacing: Area bound by Pennsylvania, Western, 164th and 178th St

Residential Resurfacing: Area bound by Rockwell, Council, NW 122nd and Hefner Rd

Residential Resurfacing: Area bound by Rockwell, Council, NW 122nd and Hefner Rd

Residential Resurfacing: Area bound by S Western, SW 29th, Shields and Oklahoma River

Residential Resurfacing: Area Bound by SE 59th, Harrah Rd, Katy St and Old Town St

Residential Resurfacing: Area bounded by I-44, SW 89th St, S May Ave and SW 74th St - SE quarter section

Residential Resurfacing: Area bounded by N Kelley Ave, NE 23rd St, N MLK Ave and NE 36th St - SW quarter section

Residential Resurfacing: Area bounded by N Pennsylvania, Nichols Hills city limit, Waverly Ave and The Village city limit

Residential Resurfacing: Area bounded by N Portland Ave, NW 63rd St, N May Ave and W Wilshire Blvd - SE quarter section

Residential Resurfacing: Area bounded by N Prospect Ave, N Martin Luther King Ave, NE 50th St and NE 58th St (Concrete work using PM-0284)

Residential Resurfacing: Area bounded by Rockwell, Hefner, Westlake Dr and Elk Canyon Dr - Canyon North Neighborhood

Residential Resurfacing: Area bounded by S May Ave, SW 89th St, S Pennsylvania Ave and SW 74th St - NE quarter section

Residential Resurfacing: Area bounded by S Santa Fe Ave, SE 29th St, S High Ave and SE 15th St - SW quarter section

Residential Resurfacing: Area bounded by S Santa Fe Ave, SE 44th St, S High Ave and SE 29th St - NW quarter section

Residential Resurfacing: Area bounded by S Sooner Rd, SE 89th St, S Air Depot Blvd and SE 74th St - SW quarter section

Residential Resurfacing: Area bounded by SE 164th, Air Depot, SE 157th Pl and Gossamer Way - Sterling Canyon Neighborhood

Residential Resurfacing: SW 44th and Cemetary Rd - Gemstone Acres

Residential Resurfacing: Rock Knoll Neighborhood - area bounded by Rockwell, Britton, Candlewood and Whitehall

Residential Resurfacing: The Landing - SE 104th St and Harrah Rd.

Residential Resurfacing: Turtle Lake - SE 149th St and Sooner Rd.

Sidewalks: NW 140TH ST & N PENNSYLVANIA AVE

Sidewalks: SW 25TH ST: S VILLA AVE TO S WESTERN AVE

Sidewalks: SW 29TH ST & S MAY AVE

Sidewalks: NW 30TH ST: WINDSOR BLVD TO N MERIDIAN AVE

Sidewalks: Along N. Classen Ave. from NW 13th St. to NW 48th St.; In the Asian District between N. Blackwelder Ave. and N. Shartel Ave., NW 30th St. and NW 25th St. (Local Match for MC-0619 NW BRT)

Sidewalks: Along N. May Ave. from N. Grand Blvd. to NW 47th St.; NW 63rd St. from N. Warren Ave. to N. Villa Ave. Work Order for TLS to update NW Expressway and NW 63rd.

Sidewalks: Along Portland Ave to connect Southlake Elementary to neighborhood.

Sidewalks: Along S. Pennsylvania Ave. from SW 29th St. to SW Grand Blvd.; Along S. Blackwelder Ave. from SW 29th St. to SW Grand Blvd.; Surrounding Heronville ES

Sidewalks: Angie Debo ES

Sidewalks: N Ann Arbor from NW 23rd St to NW 36th St

Sidewalks: Area near Prairie Queen ES

Sidewalks: Denniston Park area sidewalks

Sidewalks: Downtown OKC

Sidewalks: E.W. Perry Park

Sidewalks: GRAND BLVD: RANCHO TO S INDIANA AVE

Sidewalks: Harvest Hills

Sidewalks: Highland Park ES

Sidewalks: In the area bounded by NE 23rd St., N. Lottie Ave., NE 13th St., and N. Lincoln Blvd.

Sidewalks: In the area bounded by NE 23rd St., N. MLK Ave., NE 8th St., and N. Lottie Ave.

Sidewalks: In the area bounded by the Oklahoma River, S. Central Ave., SW 29th St., and S. Western Ave.

Sidewalks: In the area near SW 29th St from S Pennsylvania Ave to Blackwelder Ave

Sidewalks: Sellers Park area sidewalks

Sidewalks: N Martin Luther King Blvd and NE 23rd St area

Sidewalks: Multiple locations: Classen at Belle Isle, between Main St and Linwood Ave, S May Ave at SW 44th St, N Kelley Ave at NE 36th St, and N Rockwell Ave at NW 10th St

Sidewalks: Northridge ES

Sidewalks: Pied Piper and Britton Parks

Sidewalks: Ralph Downs ES

Sidewalks: Stockyards City

Sidewalks: Transit II

Sidewalks: VINTAGE FARMS RD TO BRIAR HOLLOW DR: SW 134TH ST (around Eastlake ES)

Sidewalks: Windsor PPA area

Sidewalks: Within 1/4 mile of NW 117th and Rockwell

Street Enhancements: "Plaza" Area along NW 16th St from Blackwelder to between Indiana and Kentucky

Street Enhancements: NE 10th St and Martin Luther King Dr.

Street Enhancements: NW 10th St from Rockwell Ave to Counci Rdl

Street Enhancements: Intersection at Linwood Boulevard/NW 6th Street and Western Avenue (CONNECTED PROJECTS PC-0672, PC-0673 &PC-0674)

Street Enhancements: Intersection of NW 10th & Vermont

Street Enhancements: Main & Western (CONNECTED PROJECTS PC-0672, PC-0673 &PC-0674)

Street Enhancements: Meridian Ave from NW 16th St to NW 26th St

Street Enhancements: Rockwell from NW 10th to NW 16th

Street Enhancements: Western Ave from NW 14th to I-40 (CONNECTED PROJECTS PC-0672, PC-0673 &PC-0674)

Trails: Hefner Overholser Trail

Trails: Katy Trail

Trails: Lake Hefner Trail

Trails: Lake Overholser Trail

Trails: Oklahoma River North Trail

Trails: Oklahoma River South Trail

Trails: Trail SW 119th from May to Chelsea Chase

Widening: SW 8th Street from S MacArthur Boulevard to Peniel Avenue

Widening: Intersection of N Pennsylvania Ave and W Memorial Rd (ODOT) TAP3-417 0(004)AG State Job No 34170(04),

Widening: Sara Road from SW 29th Street to SW 44th Street (ODOT/OTA Agreement)

Widening: Sara Road from SW 44th Street to SW 59th Street (ODOT/OTA Agreement)



Projects Underway

Arterial Resurfacing: S Choctaw Rd from SE 89th St to SE 104th St

Arterial Resurfacing: SW 104th Street between May Avenue and I-44

Arterial Resurfacing: SW 15th Street from Grand Boulevard to Portland Avenue

Arterial Resurfacing: NW 23rd St from N May Ave to N Pennsylvania Ave

Arterial Resurfacing: SW 59th St from S May Ave to S Pennsylvania Ave

Arterial Resurfacing: SW 59th St from S May to SW 54th St

Arterial Resurfacing: SW 59th St from S Pennsylvania Ave to S Western Ave

Arterial Resurfacing: SE 59th St from S Santa Fe Ave to S High Ave

Arterial Resurfacing: SW 59th St from S Western Ave to S Walker Ave

Arterial Resurfacing: SW 59th Street from Council Road to County Line Road

Arterial Resurfacing: SE 74th Street from Santa Fe Avenue to Shields Boulevard

Arterial Resurfacing: N Broadway Ave from Dean A McGee Ave to NW 10th St

Arterial Resurfacing: W Hefner Rd from N Council Rd to N Rockwell Ave

Arterial Resurfacing: N May Ave from Memorial Rd to NW 150th St

Arterial Resurfacing: Morgan Road from Britton Road to Hefner Road

Arterial Resurfacing: N Pennsylvania Ave from Memorial Rd to NW 150th St

Arterial Resurfacing: W Reno Ave from S Portland to S May Ave

Arterial Resurfacing: South Pennsylvania Avenue from SW 59th Street to SW 44th Street

Bike Lanes: Bike facilities, along the N. Villa Ave., N. Youngs Blvd., and N. Venice Blvd. alignments between NW 62nd St. and NW 10th St. (Sales Tax only)

Bike Lanes: On General Pershing Blvd. from N. May Ave. to N. Walker Ave. - Phase I

Bike Lanes: On N. Indiana Ave. from NW 19th St. to Linwood Blvd. and on Linwood Blvd. from N. Indiana Ave. to N. Shartel Ave.

Bike Lanes: On N. Springlake Ave., N. Laird Ave., N. Kelley Ave., and N. Phillips Dr. from N. Martin Luther Kind Ave. to NE 13th St.

Bike Lanes: On NE 24th St./N. Lottie Ave. from N. Kelley Ave. to NE 23rd St.; and on N. Lottie Ave. from NE 23rd St. to NE 4th St.

Bike Lanes: On NW Grand Blvd. and N. Independence Ave. to connect to the Bert Cooper Trails (CONNECTED PROJECTS TC-0508, TC-0545 & MS-0096).

Bike Lanes: On SE 59th St. from S. Santa Fe Ave. to S. Air Depot Ave.

Bike Lanes: On SW/SE 25th St. from S. Grand Blvd. to S. High Ave.

Intersection Improvements: N Independence Avenue and NW Expressway (CONNECTED PROJECTS TC-0508, TC-0545, MS-0096)

Intersection Improvements: Kingsgate Drive and SW 119 Street

Intersection Improvements: S Miller Avenue and SW 59 Street

Intersection Improvements: S Pennsylvania Avenue at Shadowlake Drive

Intersection Improvements: N Rockwell Avenue and NW Expressway

Intersection Improvements: Sara Road and SW 29th Street - Child Project of PC-0549

Intersection Improvements: S Sooner Road and Embers Drive/SE 48 Street

Residential Resurfacing: Area bound by I-44, W Reno, N May and NW 10th St

Residential Resurfacing: Area bound by May, Pennsylvania, SW 29th and SW 44th St

Residential Resurfacing: Area bound by May, Pennsylvania, SW 29th and SW 44th St

Residential Resurfacing: Area bound by May, Portland, SW 29th, and SW 15th

Residential Resurfacing: Area bound by NE 10th, NE 23rd, MLK and I-35

Residential Resurfacing: Area bound by S May, Pennsylvania, SW 59th and I-240

Residential Resurfacing: Area bound by S May, Pennsylvania, SW 59th and I-240

Residential Resurfacing: Area bound by Western, Pennsylvania, SW 44th and SW 29th St

Sidewalks: Along N Portland Aveniue from N Reno Avenue to NW 10th Street MS-0117 and PC-0705 tied together

Sidewalks: Along N. Pennsylvania Ave. from NW 36th St. to NW 10th St.; along NW 23rd St. from N. Villa Ave. to N. Western Ave. (ACOG/ODOT Project JP No 34171(04) Project No TAP3-4171 (004) AG)

Sidewalks: Along S Pennsylvania between SW 49th St. and SW 59th St.; along SW 59th St. from S. Villa Ave. to S. Blackwelder Ave. (ACOG/ODOT project. JP No. 34164(04) Project No. TAP3-4164 (004)AG) *future MFA request

Sidewalks: Along S. Walker Ave. from S. Grand Blvd. to SW 59th St.; along SW 44th St. from S. Western Ave. to S. Santa Fe Ave.; along S. Robinson Ave. from SW Grand Blvd. to SW 44th St. (ACOG/ODOT Project JP Np 34161(04) Project No. TAP3-4161 (004)AG)

Sidewalks: In the area bounded by and including NW 36th St., N. Classen Blvd., NW 10th St. and N. Villa Ave.

Sidewalks: N INDEPENDENCE AVE: NW 47TH ST TO NW 67TH ST

Sidewalks: N. Portland Ave. from NW 63rd St. to NW 50th St.; NW 50th St. from N. Portland Ave to N. Villa Ave. (ACOG/ODOT Project JP No 34162(04) Project No TAP3-4162 (004) AG)

Sidewalks: S. Blackwelder Ave. from SW Grand Blvd to SW 59th St.; S. Western Ave. from SW Grand Blvd. to SW 59th St.; SW 44th St. from S. Blackwedler Ave. to S. Western Ave.(ACOG/ODOT Project JP No 34165(04) Project No TAP3-4165 (004) AG) *future MFA request

Sidewalks: S. Western Ave., S. Walker Ave., S. Harvey Ave. and S. Robinson Ave. from SW 29th St. to SW Grand Blvd. (ACOG/ODOT Project JP No 34169(04) Project No TAP3-4169 (004) AG)

Street Enhancements: "Auto Alley" Area along N Broadway Ave from NW 4th St to W Park Pl

Street Enhancements: NW 10th from Meridian to MacArthur

Street Enhancements: NW 10th from Portland to Meridian / (MEMO SHOWS STREET ENHANCEMENT/RESURFACING)

Street Enhancements: SW 29th from Robinson to Western (CONNECTED TO PC-0700).

Street Enhancements: Area bounded by NW 39th and NW 40th Street, Pennsylvania and Youngs Blvd

Street Enhancements: N Portland Avenue from NW 10th Street to NW 23rd Street

Street Enhancements: N Portland Avenue from W Reno Avenue to NW 10th Street / MS-0117 and PC-0705 tied together

Street Enhancements: The area from Western to Penn on and around SW 29th St. (CONNECTED TO PC-0679).

Trails: Deep Fork Trail - Phase 3 - Child Project

Trails: Katy Trail Signage - Child project of MP-0545 PH II

Trails: Oklahoma River Trails Signage - Child project of MP-0545 PH II

Widening: SW 149th St from S May Ave to S Pennsylvania Ave

Widening: SW 149th Street from S Western Avenue to S Santa Fe Avenue

Widening: SW 15th Street from Mustang Road to John Kilpatrick TPK

Widening: SW 15th Street, Czech Hall Road to Mustang Road

Widening: SW 59th St from S Council Rd to S Rockwell Ave

Widening: N Cemetery Rd from W Reno Ave to NW 10th St *MFA pr Chad M. 9/29/20

Widening: N Rockwell Ave from W Memorial Rd to NW 150th St.

Widening: Sara Road between SW 15th Street and SW 29th Street



Projects Planned

Arterial Resurfacing: SW 29th Street from Western Avenue to Pennsylvania Avenue

Arterial Resurfacing: SW 29th Street from Western Avenue to Shields Blvd

Arterial Resurfacing: NW 30th St from Pennsylvania Ave to May Ave

Arterial Resurfacing: SW 104th St from S May Ave to S Pennsylvania Ave

Arterial Resurfacing: NW 10th St from Independence Ave to N Villa Ave

Arterial Resurfacing: SW 119th Street between Meridian Avenue and Rockwell Avenue

Arterial Resurfacing: NE 122nd St from N Air Depot Blvd to Midwest Blvd

Arterial Resurfacing: NE 122nd St from N Douglas Blvd to N Post Rd

Arterial Resurfacing: NE 122nd St from N Midwest Blvd to Douglas Blvd

Arterial Resurfacing: NE 122nd St from N Sooner Rd to N Air Depot Blvd

Arterial Resurfacing: NW 150th Street from Pennsylvania Avenue to Western Avenue

Arterial Resurfacing: NW 16th St from Eagle Ln to Rockwell Ave

Arterial Resurfacing: NW 16th St from N Pennsylvania Ave to N May Ave

Arterial Resurfacing: NE 178th Street from Indian Meridian to Triple X Road

Arterial Resurfacing: NW 23rd St from N Pennsylvania Ave to N Western Ave

Arterial Resurfacing: NW 23rd St from N Western to I-235 (CONNECTED PROJECTS PC-0648 & PC-0780)

Arterial Resurfacing: SW 25th St from S Western Ave to S Pennsylvania Ave

Arterial Resurfacing: W Memorial Rd (Westbound) from N Pennsylvania Ave to N May Ave

Arterial Resurfacing: N Rockwell Ave from W Wilshire Blvd to W Britton Rd

Arterial Resurfacing: NW 36th St from N Pennsylvania Ave to N Western Ave

Arterial Resurfacing: NW 36th St from N Portland Ave to N May Ave

Arterial Resurfacing: SE 44th St from S Douglas Blvd to S Post Rd

Arterial Resurfacing: SE 44th St from S Hiwassee Rd to S Henney Rd

Arterial Resurfacing: SW 44th Street between Frisco Road & Richland Road

Arterial Resurfacing: NW 50th St from N May Ave to N Pennsylvania Ave

Arterial Resurfacing: NE 63rd St from N Bryant Ave to 1200' E of N MLK Ave

Arterial Resurfacing: NE 63rd St from N Kelley Ave to N Martin Luther King Ave

Arterial Resurfacing: NE 63rd St from N Midwest Blvd to N Douglas Blvd

Arterial Resurfacing: NE 63rd St from N Santa Fe Ave to N Kelley Ave

Arterial Resurfacing: SE 74th Street between Henney Road and Jesse Trail

Arterial Resurfacing: SE 74th Street from Post Road to Westminster Road

Arterial Resurfacing: SE 89th St from Dobbs Rd to Harrah Rd

Arterial Resurfacing: SW 89th St from S Western Ave to S Santa Fe Ave

Arterial Resurfacing: SE 89th Street from Bryant Avenue to Sunnylane Road

Arterial Resurfacing: SE 89th Street from Luther Road to Dobbs Road

Arterial Resurfacing: S Air Depot Blvd from SE 149th to SE 164th St

Arterial Resurfacing: N Ann Arbor from NW 23rd St to NW 36th St

Arterial Resurfacing: Arterial Resurfacing: N MacArthur Boulevard from W Hefner Road to NW 122nd Street

Arterial Resurfacing: N Coltrane Rd from NE 63rd St to E Wilshire Blvd

Arterial Resurfacing: County Line Road between Hefner Road to NW 122nd Street

Arterial Resurfacing: S Douglas Blvd from SE 59th St to SE 44th St

Arterial Resurfacing: S Douglas Blvd from SE 74th St to SE 59th St

Arterial Resurfacing: N I-35 Service Rd (Northbound) from NE 23rd St to NE 36th St

Arterial Resurfacing: N I-35 Service Rd (Southbound) from NE 29th St to NE 36th St

Arterial Resurfacing: N MacArthur Blvd from W Wilshire Blvd to W Britton Rd

Arterial Resurfacing: W Memorial Rd (Eastbound) from Lake Hefner Parkway to N May Ave

Arterial Resurfacing: W Memorial Rd (Eastbound) from N May Ave to N Penn Ave

Arterial Resurfacing: W Memorial Rd from N Morgan Rd to dead end

Arterial Resurfacing: N MLK Ave from NE 23rd St to NE 36th St

Arterial Resurfacing: S Morgan Rd from SW 15th St to SW 29th St

Arterial Resurfacing: S Peebly Rd from SE 74th St to SE 59th St

Arterial Resurfacing: N Pennsylvania Ave from NW 10th St to NW 23rd St

Arterial Resurfacing: N Pennsylvania Ave from NW 122nd St to Memorial Rd

Arterial Resurfacing: N Portland Ave from Lake Shore Drive to NW 50th St

Arterial Resurfacing: S Portland Ave from SW 104th St to I-44 Service Rd

Arterial Resurfacing: S Portland Ave from SW 44th St to SW 29th St

Arterial Resurfacing: Portland Avenue from NW 39th Street to NW 50th Street

Arterial Resurfacing: Portland Avenue from SW 119th Street to SW 134th Street ***Child project of PJ-CL-0060

Arterial Resurfacing: W Reno Ave (Eastbound) from N Meridian Ave to N Portland Ave

Arterial Resurfacing: W Reno Ave (Westbound) from N Portland to N Meridian Ave

Arterial Resurfacing: W Reno Ave from N Western Ave to N Pennsylvania Ave

Arterial Resurfacing: W Reno Avenue from Council Road to Rockwell Avenue

Arterial Resurfacing: N Rockwell Ave from W Hefner Rd to NW 122nd St

Arterial Resurfacing: S Santa Fe Ave from SW 44th St to SW 29th St

Arterial Resurfacing: N Sara Rd from W Hefner Rd to NW 122nd St

Arterial Resurfacing: N Sara Rd from W Memorial Rd to NW 122nd St

Arterial Resurfacing: Sara Road from Memorial Road to NW 150th Street

Arterial Resurfacing: N Sooner Rd from E Britton Rd to E Hefner Rd

Arterial Resurfacing: N Sooner Rd from E Hefner Rd to NE 122nd St

Arterial Resurfacing: N Sooner Rd from E Wilshire Blvd to E Britton Rd

Arterial Resurfacing: Street Resurfacing: N Cemetary Rd from W Wilshire Blvd to W Britton Rd

Arterial Resurfacing: Street Resurfacing: SW 104th St from S Western Ave to S Santa Fe Ave

Arterial Resurfacing: Sunnylane Road from SE 104th Street to SE 119th Street

Arterial Resurfacing: N Walker Ave from NW 10th St to Robert S Kerr Ave

Arterial Resurfacing: S Walker Ave from SW 104th St to SW 89th St

Arterial Resurfacing: N Western Ave from N Classen Blvd to NW 18th St

Arterial Resurfacing: W Wilshire Blvd from Elmwood Ave to N May Ave

Arterial Resurfacing: Wilshire Blvd, Spencer Jones Rd east to City Limit

Bike Lanes: On N. Agnew Ave. from NW 10th St. to SW 29th St.

Bike Lanes: On W. Wilshire Blvd. from Harvest Hills Rd. to NW Expressway

Intersection Improvements: NW 36th St and Walker Ave

Intersection Improvements: NW 63 Street at N Villa Avenue

Intersection Improvements: N County Line Road and NW Expressway

Intersection Improvements: W Hefner Road at Basswood Canyon Road

Intersection Improvements: N Hudson Avenue and W Britton Road

Intersection Improvements: N Pennsylvania Avenue and NW 10th Street and Virginia Avenue

Residential Resurfacing: Area bound by NW 36th, Pennsylvania, NW Expwy and Classen Blvd.

Residential Resurfacing: Area bound by Pennsylvania, Western, SW 119th and SW 104th

Residential Resurfacing: Area bound by Western, Broadway, Britton, and Hefner Rd

Residential Resurfacing: Area bounded by I-240, SE 74th, Anderson and Hiwassee Rd

Residential Resurfacing: Area bounded by N County Line Rd, W Hefner Rd, N Council Rd and NW 122nd St - SE quarter section

Residential Resurfacing: Area bounded by N Eastern Ave, N Bryant Ave, E Britton Rd and E Hefner Rd

Residential Resurfacing: Area bounded by Reno, NW 10th, Pennsylvania and N Western Ave. Phase II NE Quadrant

Residential Resurfacing: Area bounded by Reno, NW 10th, Pennsylvania and N Western Ave. Phase I SW Quadrant

Residential Resurfacing: Area bounded by Reno, NW 10th, Pennsylvania and N Western Ave. Phase III NW Quadrant

Residential Resurfacing: Area bounded by Reno, NW 10th, Pennsylvania and N Western Ave. Phase IV SE Quadrant

Residential Resurfacing: Area bounded by S Pennsylvania Ave, SW 15th St, S Western Ave and W Reno Ave - SE quarter section

Residential Resurfacing: Area bounded by S Pennsylvania Ave, SW 89th St, S Western Ave and I-240 - NW quarter section (Concrete work using PM-0284)

Sidewalks: Along SW 59th St. from S. Blackwelder Ave. to S. Santa Fe Ave.; On S. Western Ave. from SW 59th St. to SW 62nd St.; On S. Walker Ave. from SW 59th St. to SW 62nd St.

Sidewalks: In the area bounded by SW Grand Blvd., S. Blackwelder Ave., SW 49th St., and S. Villa Ave.

Street Enhancements: "Paseo" Area between NW 30th and NW 27th St, between Harvey and Shartel

Street Enhancements: "Stockyards" Area bounded by the Oklahoma River to SW 15th from the Stockyards-OKC City limit boundary to Pennsylvania Ave

Street Enhancements: NW 10th & Penn/Virginia

Street Enhancements: NE 23rd St. from Kelley to Miramar/KatyTrail

Street Enhancements: NW 23rd Street from Western Ave to Broadway Ave (CONNECTED PROJECTS PC-0648 & PC-0780) (MEMO SHOWS STREET ENHANCEMENT/RESURFACING)

Street Enhancements: Bike lanes W. Britton Rd to SW 104th along Walker and Shartel; Council to I-35 along SW 16th and SW 19th St (PC-0516-I)

Street Enhancements: N Classen Boulevards from W Sheridan Avenue to NW 10th Street PC-0701, PC-0729, DC-0230 tied together

Street Enhancements: Portland Ave. from NW 23rd to NW 36th St

Street Enhancements: The area from Penn to May on and around SW 29th St.

Street Enhancements: Walker Avenue from NW 23rd to NW 36th Street

Trails: Bert Cooper Trail - Lake Hefner

Trails: Bert Cooper Trail Signage - child project of MP-0545-II

Trails: Greenway extending from Harvey and NW 22nd to NW 37th and Francis by following natural water features as possible

Trails: Hefner Overholser Trail Signage - Child project of MP-0545 PH II

Trails: NW Expressway and Wilshire Blvd (trails portion of 17 Bond)

Trails: Lake Overholser Trail Signage - Child project of MP-0545 PH II

Trails: Lightning Creek Trail

Trails: Lightning Creek Trail Signage - Child project of MP-0545 PH II

Trails: Trail from Agnew across the Oklahoma River on abandoned rail

Widening: SW 149th St from S Pennsylvania Ave to S Western Ave

Widening: SW 29th St from S Rockwell Ave to S MacArthur Blvd

Widening: SW 59th St from County Line Rd to Hwy 152

Widening: Czech Hall Road, Reno Avenue to SW 15th Street

Widening: S Harrah Rd from I-40 north to city limits (Oklahoma County responsible for A/E)



Remaining Proceeds

In addition to the above, there is an estimated $63,263,455 that has not yet been associated with a specific project. Based on future needs and the recommendation and approval of the Bond Advisory Commitee, the Community and Neighborhood Enhancement Advisory Board and the Mayor and Council, additional projects will be added to the list as they are identified and approved.


Below is a link to an interactive map showing the location of these projects:

Better Streets Safer City Summary Map


Glossary of Terms

Bond Advisory Committee: nine-member committee, composed of one member from each ward and one at-large member, hears requests for major reallocations of bond monies in general bond funds and makes recommendations to the Council.


Community and Neighborhood Enhancement Advisory Board (CNEAB): eleven-member appointed committee, oversees the street, sidewalk and trail projects included in the Better Streets, Safer City sales tax initiative.


Arterial: is a high-capacity road whose primary function is to deliver traffic from collector (residential) roads to other arterial roadways or freeways.


Intersection Improvements: improvements may include replacement of traffic control equipment, materials and/or technology improvements.


Street Enhancements: improvements may include landscape, amenities such as benches and/or trash receptacles, lighting and sidewalks.


Sidewalk: constructed from concrete to include ADA ramps and tactile domes.


Trail: typically, wider than a sidewalk and constructed from asphalt.


Widening: improvements include increasing the roadway width from 2 to 4 lanes.